PRINCE2-FOUNDATION · Question #646
On which environment is PRINCE2 based?
The correct answer is B. Customer/supplier. See the full explanation below for the reasoning.
Question
On which environment is PRINCE2 based?
Options
- AInformation technology
- BCustomer/supplier
- CProcurement
- DProgramme
How the community answered
(46 responses)- A15% (7)
- B78% (36)
- C2% (1)
- D4% (2)