What role is responsible for creating a Team Plan in the Managing Product Delivery process?
The correct answer is B. Team Manager. See the full explanation below for the reasoning.
Question
What role is responsible for creating a Team Plan in the Managing Product Delivery process?
Options
- AProject Manager
- BTeam Manager
- CProject Support
- DSenior User
How the community answered
(31 responses)- A10% (3)
- B81% (25)
- C6% (2)
- D3% (1)