What is the trigger for the Starting up a Project process?
The correct answer is C. Project mandate. See the full explanation below for the reasoning.
Question
What is the trigger for the Starting up a Project process?
Options
- AProject Brief
- BProject Plan
- CProject mandate
- DOutline Business Case
How the community answered
(38 responses)- A8% (3)
- B11% (4)
- C79% (30)
- D3% (1)