PeopleCert
PRINCE2-FOUNDATION · Question #62
What should be reviewed as part of preparing a Work Package?
The correct answer is B. The appropriate Product Descriptions. See the full explanation below for the reasoning.
Question
What should be reviewed as part of preparing a Work Package?
Options
- AThe Issue Log
- BThe appropriate Product Descriptions
- CProject Board Authorisation to Proceed
- DTimesheets
How the community answered
(21 responses)- A10% (2)
- B71% (15)
- C14% (3)
- D5% (1)
Community Discussion