nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #607

Which is NOT established as part of the Starting Up a Project process?

The correct answer is D. A plan for how and when a measurement of the achievement of the project's benefits can. See the full explanation below for the reasoning.

Question

Which is NOT established as part of the Starting Up a Project process?

Options

  • AA Plan for the work of initiation
  • BInformation on the various ways the project can be delivered
  • CA description of what the project is to deliver
  • DA plan for how and when a measurement of the achievement of the project's benefits can

How the community answered

(25 responses)
  • A
    8% (2)
  • B
    4% (1)
  • C
    4% (1)
  • D
    84% (21)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice