PRINCE2-FOUNDATION · Question #604

Identify the missing words in the following sentence.... The Managing a Stage Boundary process is predicated on dividing the project into [?]

The correct answer is B. Management stages. See the full explanation below for the reasoning.

Question

Identify the missing words in the following sentence.... The Managing a Stage Boundary process is predicated on dividing the project into [?]

Options

  • AStage tolerances
  • BManagement stages
  • CTechnical Stages
  • DWork Packages

How the community answered

(36 responses)
  • A
    11% (4)
  • B
    81% (29)
  • C
    3% (1)
  • D
    6% (2)