PRINCE2-FOUNDATION · Question #600

When are Work Package tolerances agreed?

The correct answer is A. When accepting a Work Package. See the full explanation below for the reasoning.

Question

When are Work Package tolerances agreed?

Options

  • AWhen accepting a Work Package
  • BWhen approving a Stage Plan
  • CWhen creating the Project Plan
  • DWhen creating the Project Brief

How the community answered

(26 responses)
  • A
    81% (21)
  • B
    4% (1)
  • C
    4% (1)
  • D
    12% (3)