PRINCE2-FOUNDATION · Question #600
When are Work Package tolerances agreed?
The correct answer is A. When accepting a Work Package. See the full explanation below for the reasoning.
Question
When are Work Package tolerances agreed?
Options
- AWhen accepting a Work Package
- BWhen approving a Stage Plan
- CWhen creating the Project Plan
- DWhen creating the Project Brief
How the community answered
(26 responses)- A81% (21)
- B4% (1)
- C4% (1)
- D12% (3)