nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #596

Which is the base product against which the Project Board and Project Manager can assess progress, issues and questions regarding ongoing viability?

The correct answer is C. Project Initiation Documentation. See the full explanation below for the reasoning.

Question

Which is the base product against which the Project Board and Project Manager can assess progress, issues and questions regarding ongoing viability?

Options

  • ABenefits Review Plan
  • BProject Brief
  • CProject Initiation Documentation
  • DProduct Status Account

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    9% (3)
  • C
    76% (25)
  • D
    12% (4)

Community Discussion

No community discussion yet for this question.