PRINCE2-FOUNDATION · Question #59

When should an initial examination of a Project Issue be performed?

The correct answer is A. As soon as it is logged. See the full explanation below for the reasoning.

Question

When should an initial examination of a Project Issue be performed?

Options

  • AAs soon as it is logged
  • BOn a weekly basis
  • CAt the next execution of the sub-process, Reviewing Stage Status
  • DAt end stage assessment

How the community answered

(62 responses)
  • A
    82% (51)
  • B
    10% (6)
  • C
    3% (2)
  • D
    5% (3)