PRINCE2-FOUNDATION · Question #588
Which is NOT an objective of the Directing a Project process?
The correct answer is C. Ensure there is a common understanding of the reasons for doing the project. See the full explanation below for the reasoning.
Question
Which is NOT an objective of the Directing a Project process?
Options
- AEnsure the plans for realizing the post-project benefits are managed and reviewed
- BProvide corporate or programme management with an interface to the project
- CEnsure there is a common understanding of the reasons for doing the project
- DEnsure there is authority to close the project
How the community answered
(17 responses)- A18% (3)
- B6% (1)
- C71% (12)
- D6% (1)