PRINCE2-FOUNDATION · Question #585

Which process can trigger a premature close of the project?

The correct answer is A. Directing a Project. See the full explanation below for the reasoning.

Question

Which process can trigger a premature close of the project?

Options

  • ADirecting a Project
  • BControlling a Stage
  • CManaging a Stage Boundary
  • DClosing a Project

How the community answered

(27 responses)
  • A
    78% (21)
  • B
    11% (3)
  • C
    7% (2)
  • D
    4% (1)

Community Discussion

No community discussion yet for this question.