Which is a specific responsibility of Project Assurance?
The correct answer is C. Reporting highlights to the Project Board. See the full explanation below for the reasoning.
Question
Which is a specific responsibility of Project Assurance?
Options
- AApproving the Risk Management Strategy
- BGiving ad-hoc direction to the Project Manager
- CReporting highlights to the Project Board
- DEnsuring the right people are planned to be involved in quality inspection
How the community answered
(33 responses)- A9% (3)
- B3% (1)
- C73% (24)
- D15% (5)