Which of the following management levels sits outside of the project management team?

The correct answer is C. Corporate or programme management. See the full explanation below for the reasoning.

Question

Which of the following management levels sits outside of the project management team?

Options

  • ADirecting
  • BManaging
  • CCorporate or programme management
  • DDelivering

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    7% (2)
  • C
    79% (22)
  • D
    11% (3)