Which of the following shows the scope of a plan?

The correct answer is B. The related Plan's product breakdown structure. See the full explanation below for the reasoning.

Question

Which of the following shows the scope of a plan?

Options

  • AThe full content of a Product Status Account for a related Work Package
  • BThe related Plan's product breakdown structure
  • CThe composition section of a Project Product Description
  • DAll of the project's Configuration Item Records

How the community answered

(59 responses)
  • A
    8% (5)
  • B
    83% (49)
  • C
    3% (2)
  • D
    5% (3)