Which of the following shows the scope of a plan?
The correct answer is B. The related Plan's product breakdown structure. See the full explanation below for the reasoning.
Question
Which of the following shows the scope of a plan?
Options
- AThe full content of a Product Status Account for a related Work Package
- BThe related Plan's product breakdown structure
- CThe composition section of a Project Product Description
- DAll of the project's Configuration Item Records
How the community answered
(59 responses)- A8% (5)
- B83% (49)
- C3% (2)
- D5% (3)