A pre-requisite of effective issue and change control is the establishment of which of the following?
The correct answer is C. A configuration management system. See the full explanation below for the reasoning.
Question
A pre-requisite of effective issue and change control is the establishment of which of the following?
Options
- AUse of a change budget and change authority
- BA risk management procedure
- CA configuration management system
- DA quality management strategy
How the community answered
(62 responses)- A8% (5)
- B16% (10)
- C73% (45)
- D3% (2)