A pre-requisite of effective issue and change control is the establishment of which of the following?

The correct answer is C. A configuration management system. See the full explanation below for the reasoning.

Question

A pre-requisite of effective issue and change control is the establishment of which of the following?

Options

  • AUse of a change budget and change authority
  • BA risk management procedure
  • CA configuration management system
  • DA quality management strategy

How the community answered

(62 responses)
  • A
    8% (5)
  • B
    16% (10)
  • C
    73% (45)
  • D
    3% (2)