PRINCE2-FOUNDATION · Question #534

Which of the following is a request for change?

The correct answer is D. Although it has passed quality control, a user would like to suggest an increase in the. See the full explanation below for the reasoning.

Question

Which of the following is a request for change?

Options

  • AThe Executive feels that the project product may not be of sufficient quality in order to
  • BThe Project Manager has been advised that a team member has been taken ill and so the
  • CThe supplier needs to amend a product because it does not conform to its quality criteria
  • DAlthough it has passed quality control, a user would like to suggest an increase in the

How the community answered

(51 responses)
  • A
    6% (3)
  • B
    2% (1)
  • C
    12% (6)
  • D
    80% (41)