PRINCE2-FOUNDATION · Question #534

PRINCE2-FOUNDATION Question #534: Real Exam Question with Answer & Explanation

Sign in or unlock PRINCE2-FOUNDATION to reveal the answer and full explanation for question #534. The question stem and answer options stay visible for context.

Question

Which of the following is a request for change?

Options

  • AThe Executive feels that the project product may not be of sufficient quality in order to
  • BThe Project Manager has been advised that a team member has been taken ill and so the
  • CThe supplier needs to amend a product because it does not conform to its quality criteria
  • DAlthough it has passed quality control, a user would like to suggest an increase in the