What product is reviewed by the Project Manager as part of progress assessment to determine whether a Work Package is performing to the agreed cost and time tolerances?

The correct answer is B. Checkpoint Report. See the full explanation below for the reasoning.

Question

What product is reviewed by the Project Manager as part of progress assessment to determine whether a Work Package is performing to the agreed cost and time tolerances?

Options

  • AHighlight Report
  • BCheckpoint Report
  • CException Report
  • DOff-specification

How the community answered

(32 responses)
  • A
    9% (3)
  • B
    69% (22)
  • C
    6% (2)
  • D
    16% (5)