PRINCE2-FOUNDATION · Question #520

What is produced by the Project Manager to define and keep control of the work to build products?

The correct answer is D. Work Package. See the full explanation below for the reasoning.

Question

What is produced by the Project Manager to define and keep control of the work to build products?

Options

  • AProduct Status Account
  • BCheckpoint Report
  • CHighlight Report
  • DWork Package

How the community answered

(29 responses)
  • A
    7% (2)
  • B
    14% (4)
  • C
    3% (1)
  • D
    76% (22)