nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #514

Which of the following is mandatory in a PRINCE2 project?

The correct answer is B. Use of management stages. See the full explanation below for the reasoning.

Question

Which of the following is mandatory in a PRINCE2 project?

Options

  • AUse of a separate person as Team Manager
  • BUse of management stages
  • CUse of Exception Plans
  • DUse of Team Plans

How the community answered

(44 responses)
  • A
    7% (3)
  • B
    77% (34)
  • C
    14% (6)
  • D
    2% (1)

Community Discussion