Which of the following is mandatory in a PRINCE2 project?
The correct answer is B. Use of management stages. See the full explanation below for the reasoning.
Question
Which of the following is mandatory in a PRINCE2 project?
Options
- AUse of a separate person as Team Manager
- BUse of management stages
- CUse of Exception Plans
- DUse of Team Plans
How the community answered
(44 responses)- A7% (3)
- B77% (34)
- C14% (6)
- D2% (1)