PeopleCert
PRINCE2-FOUNDATION · Question #507
PRINCE2-FOUNDATION Question #507: Real Exam Question with Answer & Explanation
Sign in or unlock PRINCE2-FOUNDATION to reveal the answer and full explanation for question #507. The question stem and answer options stay visible for context.
Question
What factors need to be taken into consideration when identifying the number of management stages required? 1. Where key decisions points need to be 2. The amount of risk within the project 3. The number of technical stages 4. How confident the Project Board and Project Manager are with proceeding
Options
- A1,2,3
- B1,2,4
- C1,3,4
- D2,3,4
Unlock PRINCE2-FOUNDATION to see the answer
You've previewed enough free PRINCE2-FOUNDATION questions. Unlock PRINCE2-FOUNDATION for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.