PRINCE2-FOUNDATION · Question #504
How does the Progress theme assist the Project Board to assess project viability at regular intervals?
The correct answer is B. Only one management stage is authorized at a time. See the full explanation below for the reasoning.
Question
How does the Progress theme assist the Project Board to assess project viability at regular intervals?
Options
- ASends regular Checkpoint Reports to the Project Board
- BOnly one management stage is authorized at a time
- CCreates Exception Reports when tolerances are forecast to be exceeded
- DReports to the Project Board during project closure
How the community answered
(42 responses)- A2% (1)
- B81% (34)
- C7% (3)
- D10% (4)