PRINCE2-FOUNDATION · Question #501

Which product is used to inform the Project Board of a forecast deviation of stage-level tolerance?

The correct answer is B. Exception Report. See the full explanation below for the reasoning.

Question

Which product is used to inform the Project Board of a forecast deviation of stage-level tolerance?

Options

  • AException Plan
  • BException Report
  • COff-specification
  • DHighlight Report

How the community answered

(46 responses)
  • A
    7% (3)
  • B
    76% (35)
  • C
    13% (6)
  • D
    4% (2)

Community Discussion

No community discussion yet for this question.