Which of the following is NOT a step within the risk management procedure?

The correct answer is D. Propose. See the full explanation below for the reasoning.

Question

Which of the following is NOT a step within the risk management procedure?

Options

  • AAssess
  • BCommunicate
  • CPlan
  • DPropose

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    14% (3)
  • C
    5% (1)
  • D
    77% (17)