PRINCE2-FOUNDATION · Question #475
Which of the following best defines a project output?
The correct answer is D. Any one of the project's specialist products. See the full explanation below for the reasoning.
Question
Which of the following best defines a project output?
Options
- AThe information required for decision-making purposes
- BThe measurable improvement resulting from an outcome
- CThe result of the change derived from using the project's outputs
- DAny one of the project's specialist products
How the community answered
(63 responses)- A3% (2)
- B11% (7)
- C5% (3)
- D81% (51)