A project being output oriented supports which PRINCE2 principle?
The correct answer is A. Focus on products. See the full explanation below for the reasoning.
Question
A project being output oriented supports which PRINCE2 principle?
Options
- AFocus on products
- BDefined roles and responsibilities
- CManage by stages
- DContinued business justification
How the community answered
(32 responses)- A72% (23)
- B9% (3)
- C3% (1)
- D16% (5)