Question

Which of the following are functions of the start-up process, SU? 1) Setting up the project management team 2) Developing the Project Mandate into the Project Brief 3) Confirming the Project Approach 4) Creating the Issue Log

Options

  • AAll four
  • Bthe first three
  • Cthe first two
  • Dthe third is wrong