PeopleCert
PRINCE2-FOUNDATION · Question #469
What environment does PRINCE2 assume?
The correct answer is B. Customer/Supplier. See the full explanation below for the reasoning.
Question
What environment does PRINCE2 assume?
Options
- AThird party
- BCustomer/Supplier
- CFixed-price contract
- DManagement and Specialist
How the community answered
(36 responses)- A8% (3)
- B69% (25)
- C3% (1)
- D19% (7)
Community Discussion
No community discussion yet for this question.