PRINCE2-FOUNDATION · Question #457

If used, in which process would a Team Plan be created?

The correct answer is A. Managing Product Delivery. See the full explanation below for the reasoning.

Question

If used, in which process would a Team Plan be created?

Options

  • AManaging Product Delivery
  • BManaging a Stage Boundary
  • CDirecting a Project
  • DControlling a Stage

How the community answered

(28 responses)
  • A
    75% (21)
  • B
    14% (4)
  • C
    7% (2)
  • D
    4% (1)