PRINCE2-FOUNDATION · Question #448

Which of the following is carried out as part of the Initiating a Project process?

The correct answer is B. Ensure there is a common understanding of the reasons for doing the project. See the full explanation below for the reasoning.

Question

Which of the following is carried out as part of the Initiating a Project process?

Options

  • AEnsure there is authority to deliver the project's products
  • BEnsure there is a common understanding of the reasons for doing the project
  • CAppoint the Executive and Project Manager
  • DCreate a stage Plan for the next stage of the project

How the community answered

(18 responses)
  • A
    11% (2)
  • B
    78% (14)
  • C
    6% (1)
  • D
    6% (1)