Question

According to PRINCE2, which of the following statements is FALSE regarding project closure?

Options

  • AA clear end to the project gives recognition that the original objectives have been met
  • BA clear end to the project provides an opportunity to ensure that all unachieved goals and
  • CA clear end to the project enables the organization to understand the work that needs to be
  • DA clear end to the project transfers ownership of the products to the customer