PRINCE2-FOUNDATION · Question #432

Which process covers the activities of those at the level of management above the Project Manager?

The correct answer is C. Directing a Project. See the full explanation below for the reasoning.

Question

Which process covers the activities of those at the level of management above the Project Manager?

Options

  • AControlling a Stage
  • BManaging a Stage Boundary
  • CDirecting a Project
  • DManaging Product Delivery

How the community answered

(29 responses)
  • A
    3% (1)
  • B
    14% (4)
  • C
    76% (22)
  • D
    7% (2)