nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #427

In which process may a premature close of the project be authorized?

The correct answer is A. Directing a Project. See the full explanation below for the reasoning.

Question

In which process may a premature close of the project be authorized?

Options

  • ADirecting a Project
  • BControlling a Stage
  • CManaging a Stage Boundary
  • DClosing a Project

How the community answered

(35 responses)
  • A
    83% (29)
  • B
    3% (1)
  • C
    6% (2)
  • D
    9% (3)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice