PRINCE2-FOUNDATION · Question #423

Which PRINCE2 role is accountable to corporate or programme management for the success of the project?

The correct answer is A. Project Board. See the full explanation below for the reasoning.

Question

Which PRINCE2 role is accountable to corporate or programme management for the success of the project?

Options

  • AProject Board
  • BProject Manager
  • CSenior User
  • DChange Authority

How the community answered

(21 responses)
  • A
    76% (16)
  • B
    14% (3)
  • C
    5% (1)
  • D
    5% (1)