PRINCE2-FOUNDATION · Question #419

PRINCE2-FOUNDATION Question #419: Real Exam Question with Answer & Explanation

Sign in or unlock PRINCE2-FOUNDATION to reveal the answer and full explanation for question #419. The question stem and answer options stay visible for context.

Question

Which PRINCE2 role has a specific responsibility for referring to the Project Board if any delegated limits of authority or allocated change budget are forecast to be exceeded?

Options

  • ATeam Manager
  • BProject Assurance
  • CChange Authority
  • DProject Manager