Which of the following is NOT a PRINCE2 definition of a project?

The correct answer is D. Uses a defined set of techniques. See the full explanation below for the reasoning.

Question

Which of the following is NOT a PRINCE2 definition of a project?

Options

  • AHas an organisation structure
  • BProduces defined and measurable business products
  • CUses a defined amount of resources
  • DUses a defined set of techniques

How the community answered

(37 responses)
  • A
    11% (4)
  • B
    3% (1)
  • C
    5% (2)
  • D
    81% (30)