Which product would be updated to show that a decision has been made on an off-specification which has now been closed?

The correct answer is C. Issue Report. See the full explanation below for the reasoning.

Question

Which product would be updated to show that a decision has been made on an off-specification which has now been closed?

Options

  • AQuality Register
  • BDaily Log
  • CIssue Report
  • DRisk Register

How the community answered

(26 responses)
  • A
    12% (3)
  • B
    4% (1)
  • C
    81% (21)
  • D
    4% (1)