Question
Which of the following is FALSE regarding the Change theme?
Options
- AChange control should be used to prevent changes being made to baselined products
- BIssues can affect the project's performance targets of time, cost, quality, scope, benefits
- CA pre-requisite of effective issue and change control would be an appropriate configuration
- DWithout issue and change control being applied, a project will become unresponsive to its