Question

Which of the following is FALSE regarding the Change theme?

Options

  • AChange control should be used to prevent changes being made to baselined products
  • BIssues can affect the project's performance targets of time, cost, quality, scope, benefits
  • CA pre-requisite of effective issue and change control would be an appropriate configuration
  • DWithout issue and change control being applied, a project will become unresponsive to its