PRINCE2-FOUNDATION · Question #326
Which statement correctly describes the differences between Project Assurance and quality assurance?
The correct answer is A. Project Assurance provides assurance to the project's stakeholders whereas quality. See the full explanation below for the reasoning.
Question
Which statement correctly describes the differences between Project Assurance and quality assurance?
Options
- AProject Assurance provides assurance to the project's stakeholders whereas quality
- BThey are both the responsibility of the Project Board, but Project Assurance may be
- CQuality assurance is internal to the project, whereas Project Assurance is independent of
- DProject Assurance must be independent of the Project Manager, whereas quality
How the community answered
(38 responses)- A79% (30)
- B3% (1)
- C5% (2)
- D13% (5)