Which of the following is FALSE regarding an Exception Report?
The correct answer is C. It replaces a Stage Plan or Project Plan. See the full explanation below for the reasoning.
Question
Which of the following is FALSE regarding an Exception Report?
Options
- AIt describes a forecast deviation of stage or project level tolerance
- BIt contains recovery options and a recommendation
- CIt replaces a Stage Plan or Project Plan
- DIt describes the consequences of the deviation
How the community answered
(41 responses)- A15% (6)
- B5% (2)
- C76% (31)
- D5% (2)