PRINCE2-FOUNDATION · Question #306

The Project Board have overall control at what level?

The correct answer is C. Project level within project tolerance. See the full explanation below for the reasoning.

Question

The Project Board have overall control at what level?

Options

  • ADay-to-day control for a management stage within stage tolerance
  • BWork Package level within Work Package tolerance
  • CProject level within project tolerance
  • DAll levels of plans and tolerances

How the community answered

(44 responses)
  • A
    5% (2)
  • B
    7% (3)
  • C
    73% (32)
  • D
    16% (7)