Which of the following is used to inform the Project Board of a forecast deviation of stage-level tolerance?

The correct answer is B. Exception Report. See the full explanation below for the reasoning.

Question

Which of the following is used to inform the Project Board of a forecast deviation of stage-level tolerance?

Options

  • AException Plan
  • BException Report
  • COff-specification
  • DLessons Report

How the community answered

(39 responses)
  • A
    13% (5)
  • B
    79% (31)
  • C
    3% (1)
  • D
    5% (2)