PRINCE2-FOUNDATION · Question #291

Which of the following products is used after the Starting Up a Project process to capture and maintain information on all of the identified threats and opportunities relating to the project?

The correct answer is B. Risk Register. See the full explanation below for the reasoning.

Question

Which of the following products is used after the Starting Up a Project process to capture and maintain information on all of the identified threats and opportunities relating to the project?

Options

  • ARisk Management Strategy
  • BRisk Register
  • CIssue Register
  • DQuality Register

How the community answered

(47 responses)
  • A
    2% (1)
  • B
    77% (36)
  • C
    13% (6)
  • D
    9% (4)