PRINCE2-FOUNDATION · Question #284
Which of the following would NOT be classified as a threat to a project?
The correct answer is B. It is possible that the product completes user acceptance testing in a single test cycle rather. See the full explanation below for the reasoning.
Question
Which of the following would NOT be classified as a threat to a project?
Options
- AA competitor may launch a rival product first thus affecting the expected market share for the
- BIt is possible that the product completes user acceptance testing in a single test cycle rather
- CA prototype may be damaged in transit
- DA critical meeting could be affected by air travel disruption
How the community answered
(39 responses)- A5% (2)
- B79% (31)
- C3% (1)
- D13% (5)