Which of the following would NOT be classified as a threat to a project?

The correct answer is B. It is possible that the product completes user acceptance testing in a single test cycle rather. See the full explanation below for the reasoning.

Question

Which of the following would NOT be classified as a threat to a project?

Options

  • AA competitor may launch a rival product first thus affecting the expected market share for the
  • BIt is possible that the product completes user acceptance testing in a single test cycle rather
  • CA prototype may be damaged in transit
  • DA critical meeting could be affected by air travel disruption

How the community answered

(39 responses)
  • A
    5% (2)
  • B
    79% (31)
  • C
    3% (1)
  • D
    13% (5)