Which of the following Plans are approved by the Project Manager?
The correct answer is B. Team Plan. See the full explanation below for the reasoning.
Question
Which of the following Plans are approved by the Project Manager?
Options
- AProject Plan
- BTeam Plan
- CException Plan
- DStage Plan
How the community answered
(30 responses)- A7% (2)
- B80% (24)
- C10% (3)
- D3% (1)