Which of the following Plans are approved by the Project Manager?

The correct answer is B. Team Plan. See the full explanation below for the reasoning.

Question

Which of the following Plans are approved by the Project Manager?

Options

  • AProject Plan
  • BTeam Plan
  • CException Plan
  • DStage Plan

How the community answered

(30 responses)
  • A
    7% (2)
  • B
    80% (24)
  • C
    10% (3)
  • D
    3% (1)