PRINCE2-FOUNDATION · Question #270
PRINCE2-FOUNDATION Question #270: Real Exam Question with Answer & Explanation
The correct answer is B. A review of the performance of the project's products in operational use and identification of. See the full explanation below for the reasoning.
Question
Which of the following would be carried out as part of a post-project benefits review?
Options
- AAn assessment of whether the project fulfilled its original objectives
- BA review of the performance of the project's products in operational use and identification of
- CAn assessment of the project's risk management procedure
- DA review of the performance of the project management method and the project