Which of the following would be carried out as part of a post-project benefits review?

Options

  • AAn assessment of whether the project fulfilled its original objectives
  • BA review of the performance of the project's products in operational use and identification of
  • CAn assessment of the project's risk management procedure
  • DA review of the performance of the project management method and the project