PRINCE2-FOUNDATION · Question #264

PRINCE2-FOUNDATION Question #264: Real Exam Question with Answer & Explanation

The correct answer is C. Business Case. See the full explanation below for the reasoning.

Question

Any project outcomes perceived as negative by one or more stakeholders would be documented in which product?

Options

  • ARisk Management Strategy
  • BIssue Register
  • CBusiness Case
  • DProject Product Description