PeopleCert
PRINCE2-FOUNDATION · Question #22
The Project Quality Plan is written in which process?
The correct answer is A. Initiating a Project. See the full explanation below for the reasoning.
Question
The Project Quality Plan is written in which process?
Options
- AInitiating a Project
- BStarting up a Project
- CManaging Stage Boundaries
- DDirecting a Project
How the community answered
(46 responses)- A76% (35)
- B7% (3)
- C13% (6)
- D4% (2)
Community Discussion