nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #20

If there is a request to change a baselined product, and the change can be done within the stage or Work Package tolerances, how can the decision to implement the change be made?

The correct answer is D. formal change control. See the full explanation below for the reasoning.

Question

If there is a request to change a baselined product, and the change can be done within the stage or Work Package tolerances, how can the decision to implement the change be made?

Options

  • AProject Manager's decision
  • BTeam Manager's decision
  • CTeam member's decision to whom the work has been allocated
  • Dformal change control

How the community answered

(22 responses)
  • A
    9% (2)
  • B
    5% (1)
  • D
    86% (19)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice