PRINCE2-FOUNDATION · Question #20
If there is a request to change a baselined product, and the change can be done within the stage or Work Package tolerances, how can the decision to implement the change be made?
The correct answer is D. formal change control. See the full explanation below for the reasoning.
Question
If there is a request to change a baselined product, and the change can be done within the stage or Work Package tolerances, how can the decision to implement the change be made?
Options
- AProject Manager's decision
- BTeam Manager's decision
- CTeam member's decision to whom the work has been allocated
- Dformal change control
How the community answered
(22 responses)- A9% (2)
- B5% (1)
- D86% (19)