Who might receive completed products before the Team Manager reports that the Work Package has been completed?

The correct answer is C. Configuration Librarian. See the full explanation below for the reasoning.

Question

Who might receive completed products before the Team Manager reports that the Work Package has been completed?

Options

  • AThe Customer
  • BThe User
  • CConfiguration Librarian
  • DThe Project Board

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    7% (2)
  • C
    85% (23)
  • D
    4% (1)