PRINCE2-FOUNDATION · Question #195
What does PRINCE2TM suggest is a direct input to the Project Quality Plan?
The correct answer is D. Customer Quality Expectations. See the full explanation below for the reasoning.
Question
What does PRINCE2TM suggest is a direct input to the Project Quality Plan?
Options
- AISO 9001
- BStage Quality Plan
- CThe supplier quality policy
- DCustomer Quality Expectations
How the community answered
(37 responses)- A8% (3)
- B3% (1)
- C16% (6)
- D73% (27)