PRINCE2-FOUNDATION · Question #195

What does PRINCE2TM suggest is a direct input to the Project Quality Plan?

The correct answer is D. Customer Quality Expectations. See the full explanation below for the reasoning.

Question

What does PRINCE2TM suggest is a direct input to the Project Quality Plan?

Options

  • AISO 9001
  • BStage Quality Plan
  • CThe supplier quality policy
  • DCustomer Quality Expectations

How the community answered

(37 responses)
  • A
    8% (3)
  • B
    3% (1)
  • C
    16% (6)
  • D
    73% (27)